2/2025 Should have 5 extra. Beginning PC replacement 4th-5th week of Feb.
in progress
c
member badge
chase.carmines@icgbuilds.com
February 27, 2025
C
member badge
Chuck Higginbotham
marked this post as
in progress
Slowly replacing PC's as needed.
·
June 16, 2025
·
Reply
C
member badge
Chuck Higginbotham
Spoke with Lauren today. She needs to turn in her request for user PC's tomorrow evening. We discussed an extra 5 user laptops and a refresh of 8 for the training room in GCS. I will follow up with her tomorrow morning.
·
April 1, 2025
·
Reply
c
member badge
chase.carmines@icgbuilds.com
This is in regards to upgrading user-PCs. Not shop floor. Also good to have some spare's to quickly swap users with issues.
·
March 11, 2025
·
Reply
c
member badge
chase.carmines@icgbuilds.com
marked this post as
submitted
·
February 27, 2025
·
Reply