The Design Combined event has been updated.
  • Revised the slack days between tasks.
  • Restored the "Submit Truss Designs to EOR" task.
  • Added a new task - "Upload Customer Options".
The task "Schedule Framing Event" is now 15 days after the takeoff is completed. This will act as a holding date and will be the task that the field and the manufacturing facilities should monitor. I have also pushed these changes out to all of the existing design jobs. (71 Total)
I have added two new favorites for all users. These will be located near top of the favorites list in the section called "Global Favorites".
  • Schedule Framing Event
  • Upload Customer Options
Below is a picture showing the location of the favorites.
image
The next picture shows the revised task flow for the Design Combined event. (Tasks in blue are milestones.)
image